Corinth-Kos power link project gets under way

IPTO has signed a contract with Hellenic Cables for the €1.48bn Corinth-Kos interconnection, which will link the Dodecanese to the mainland grid.

Corinth-Kos power link project gets under way

This article is an AI translation of an original piece published in Greek. Read original

IPTO has signed a contract with contractor Hellenic Cables for the submarine and underground power cables for the Corinth-Kos interconnection. The contract marks the start of construction on the major energy project, with the relevant seabed surveys due to begin shortly.

The project, with a total budget of €1.48bn, covers the engineering, procurement, construction and installation (EPCI) of a 320 kV high-voltage direct-current (HVDC) link between Corinth and Kos, with a transmission capacity of 1,000 MW. The cable system to be installed will have a total length of about 1,290 km.

The Corinth-Kos power link is a project of strategic importance, as it is the essential first step towards connecting the Dodecanese to the country’s mainland electricity system and ending the islands’ power isolation. Under IPTO’s investment plan, Rhodes and Karpathos will subsequently be connected directly to the high-voltage grid via Kos.

Upgrading the islands’ energy supply

As part of the Dodecanese interconnection, the stand-alone power systems of the smaller islands in the area will also be connected indirectly: Kasos, Chalki, Symi, Kalymnos, Pserimos, Telendos, Nisyros, Tilos, Leros, Lipsi, Gyali, Patmos and Arki (Marathi).

The new energy corridor will end Kos’s reliance on local fossil-fuel power plants, strengthen the island’s energy security and help make its electricity supply greener, bringing environmental benefits to the local ecosystem. The interconnection will also reduce the cost of power generation and, in turn, help lower Public Service Obligation (PSO) charges, which are shared among consumers across the country.

Environment and Energy Minister Stavros Papastavrou said: «With the signing of the contract, the Corinth-Kos power link moves from planning to implementation. This is an investment worth €1.5bn and the first decisive step towards connecting the Dodecanese to the mainland electricity system and ending the islands’ energy isolation. Kos, followed by Rhodes, Karpathos and the smaller islands in the area, will have a more stable, cleaner and more affordable electricity supply, reducing their reliance on expensive oil-fired power plants. A reliable energy supply will also boost the local economy, support tourism businesses and improve the quality and competitiveness of the Dodecanese’s tourism offering. The benefits will extend to all consumers, as the interconnection will help reduce the Public Service Obligation charges added to every electricity bill. Through projects of this scale, we are bringing Greece together through its energy network and ensuring a better and more affordable electricity supply for every citizen, in every corner of our country».

IPTO Chairman and Chief Executive Officer Manos Manousakis said: «IPTO is embarking on another landmark interconnection for the country’s electricity system. The Corinth-Kos link is the second electricity transmission project using direct-current technology that IPTO has undertaken in recent years, following the Crete-Attica interconnection. Our people’s technical expertise and high level of scientific training, combined with Hellenic Cables’ experience — with which IPTO has a track record of successful collaboration on complex projects — are a guarantee of the technical quality and smooth construction of the link, which will allow the Dodecanese to be integrated into the high-voltage grid».

Cenergy Holdings Chief Executive Officer and Hellenic Cables Group General Manager Alexis Alexiou said: «We are particularly pleased to be working with IPTO on the Corinth-Kos interconnection, to which we are contributing our specialised expertise in HVDC cable systems and our experience in delivering complex turnkey projects. This is a project of strategic importance that will connect the Dodecanese to the mainland electricity grid, and we look forward to delivering it safely and reliably».

The interconnection project is co-financed through a loan from the European Investment Bank and has received a positive assessment for a grant from the Island Decarbonisation Fund and the Just Transition Mechanism.