Green light for 4,700 MW of energy storage projects

In total, projects with storage capacity of 7,770.76 MW are included in the ranking tables, with connection terms to be issued for a total capacity of up to 4,700 MW.

Green light for 4,700 MW of energy storage projects

This article is an AI translation of an original piece published in Greek. Read original

Energy storage projects with capacity of up to 4,700 MW, accelerating Greece’s energy development Greece, following the completion of the assessment of investment applications for Definitive Connection Offers for individual electricity storage stations (Government Gazette, issue ΚΑΔ 61365 Β 6819/13-11-2026).

The strong response from the investment community confirms the potential of the new regulatory framework and the pivotal role of storage in making better use of generation from renewable energy sources, reducing curtailments and creating a more flexible and reliable electricity system, the Ministry of Environment and Energy said.

A total of 831 applications were submitted, for a combined capacity of 12,319 MW. Of these, 221 applications, representing 10,521 MW, were for connection to the Transmission System operated by IPTO, while 610 applications, representing 1,798 MW, were for connection to the Distribution Network operated by HEDNO.

The assessment was carried out by the competent committee in accordance with the criteria and requirements of the regulatory framework, and resulted in the preparation of ranking tables by project category and responsible network operator.

In particular, the ranking tables for projects connecting to the Transmission System include storage stations with a total capacity of 6,366.88 MW, while the corresponding tables for the Distribution Network include stations with a total capacity of 1,403.88 MW. In total, projects with storage capacity of 7,770.76 MW are included in the ranking tables, with connection terms to be issued for a total capacity of up to 4,700 MW.

In accordance with the regulatory framework, the tables were drawn up on the basis of twice the available capacity limits for each category and the level of interest expressed, to ensure full use of the available capacity. Following their publication, IPTO and HEDNO will issue Definitive Connection Offers in order of application priority, until the limits for each project category are reached, up to a total capacity of 4,700 MW. The process will take account of the technical feasibility of connection and compliance with the prescribed anti-concentration limits.

With the assessment complete, another significant step is being taken towards the development of electricity storage in Greece. The Ministry of Environment and Energy is consistently implementing its plan so that more clean energy can be put to use and delivered to consumers, with fewer curtailments and a more efficient and reliable electricity system, the statement said. 

Minister of Environment and Energy Stavros Papastavrou said: “Greece has made a major leap in the energy transition in recent years, investing in infrastructure and projects that harness its strong energy advantage and generate an ever larger share of its electricity needs from renewable sources. The next goal is to store this energy so that we can make the most of it, delivering tangible benefits for citizens and businesses.

That is why we are accelerating the development of energy storage, with projects of up to 4,700 MW moving to the next stage. With the confidence of investors and support from the state at every level, from major infrastructure to households, farmers and businesses, we are moving ahead with the creation of an electricity system with fewer curtailments, greater security and stability, and more affordable energy for all”.