Fast-track moves for PPC’s data centre in Kozani

An offer setting out the connection terms for the mega data centre in Western Macedonia is imminent. A final agreement with Amazon is expected by March, with orders to contractors in spring and bulldozers on site in summer 2027. Scenarios for a 1 GW facility.

Fast-track moves for PPC’s data centre in Kozani
O CEO της ΔΕΗ Γιώργος Στάσσης

This article is an AI translation of an original piece published in Greek. Read original

Work is moving at speed on PPC’s mega data centre in Kozani, with the company expecting to reach a final agreement with Amazon in the first quarter of next year. That would mean orders to suppliers in spring and bulldozers on site in summer 2027.

A new legal framework is helping, giving absolute priority to projects of more than 200 MW that are supplied at least 60% by renewables, such as its own 300 MW project. The group has already submitted the relevant application and is awaiting the final connection terms from IPTO.

“We have already received preliminary connection terms from IPTO, and I expect we will soon have the final terms as well, which will represent another important step. At the same time, we are negotiating the final agreements with our partner, AWS,” CEO George Stassis said yesterday, speaking to analysts, as he discussed progress on the agreement signed in September.

Outlining the steps involved in the huge investment, estimated at 10 billion including the digital infrastructure, PPC’s management believes that, if all goes well, the construction site could be set up in the area of the former Agios Dimitrios lignite plant this summer.

That is why the CEO said yesterday that the agreement with Amazon should be finalised in the first quarter of 2027, as this period coincides with the three-month window the new law gives investors to accept IPTO’s final connection offer.

The plan to get bulldozers on site this summer

According to informed sources, PPC’s plan is to place equipment orders with contractors in spring 2027, start work immediately afterwards and complete the project by the end of 2028.

Asked when it will begin disbursing the first funds, the answer is as soon as it reaches an agreement with AWS. The Greek group’s share covers only the construction and energy infrastructure (buildings, electrical installation, etc.), estimated at around €1bn.

The second part, namely the IT infrastructure (Ethernet cabling, etc.), also estimated at €1bn, will be covered by AWS, as will the third part: the processing units (GPUs), which Amazon sources largely from NVIDIA, which controls around 80% of the global market. 

At the same time, once the two sides have agreed on the first 300 MW phase, PPC will start discussions with AWS on the second phase: developing a 1 GW data centre in Kozani. The US giant has an exclusive option on the project, which it must exercise by the end of May 2027.

If they reach an agreement, which management considers quite likely, the huge project — whose digital component would take the investment to three times as much, as much as €30bn — could get under way in autumn 2027, with the aim of being connected to the system in 2031.

Otherwise, the company will approach other interested parties. “Even if they (AWS) do not proceed, we will of course open up this opportunity to third parties. But for now, we have a commitment to AWS, under which it retains priority rights until the end of May next year,” Stassis said yesterday.

It is worth noting that, beyond construction, PPC’s obligations boil down to four agreements: a long-term lease of the land and building to AWS; the supply of green energy under a long-term contract (green PPA); an uninterrupted power supply 365 days a year, a prerequisite for a data centre; and facility management.

The first quarter of 2027 will also be challenging

Aside from the AWS deal, analysts also focused yesterday on high energy prices, management’s forecasts for the coming period and, above all, what safeguards the group has in place to withstand the severity and depth of the crisis.

“When international prices are higher, profits from energy generation increase while those from supply decline, and vice versa: higher profits from supply and lower profits from generation. This is a constant feature of our sector, at least in European markets,” Stassis said, describing the advantages of an integrated player. These also underpin the target of €2.8bn in EBITDA in 2027, up from this year’s target of €2.4bn.

He said not only the final quarter of the year but also the first quarter of 2027 would be difficult. He said price volatility would persist for months and that conditions would start to improve gradually over the course of next year. He expects PPC to have higher profitability in generation and lower profitability in supply next year as well.