The Deputy Minister for Infrastructure and Transport, Nikos Takhiaos, stressed the need to proceed with Line 4 of the Athens Metro seriously and safely for the buildings in Kypseli, speaking to radio station SKAI 100.3. He made clear that the contracting consortium is responsible for repairing damage to the apartments.
“It is the contractor’s responsibility to repair damage at its own expense and using its own resources. That is clear and not up for discussion,” he said. He added that the tunnel boring machine must restart and that this is urgent, “but it will start only if the buildings above it are safe.”
Mr Takhiaos clarified what it means for the apartment block to be designated “red”. As he explained, the designation is part of the internal procedures of Elliniko Metro and the project, and indicates how a building will be assessed based on its vulnerability. “It has nothing to do with the red classification we know from earthquakes,” he stressed, adding that at this stage no need has arisen to relocate residents from any of the buildings where work is required.
Technical measures
At this apartment block, the ground beneath the footings of the arcade’s columns is being reinforced, following a recommendation from experts at the Technical Chamber of Greece. Exploratory trenches were dug first to identify the utility networks running through the site and avoid problems in the area.
The Deputy Minister for Infrastructure and Transport explained that there are two distinct zones. In the first, the tunnel has already been built and repairs can proceed directly. In the second, the tunnel boring machine’s shield is currently beneath six buildings, which need to be supported before it can restart.
The relevant study is now being carried out. “Every building is a different case. We cannot treat them all in the same way,” he said.
Lord Robert Mair, a British professor and one of the world’s leading engineers in the field, is contributing to the effort. His recommendations are expected in about 20 days. Mr Takhiaos noted that similar issues have arisen during other tunnel excavations and have been dealt with.
Possible temporary relocation of residents
Mr Takhiaos was clear about the possibility of temporarily relocating residents. It remains an option for the duration of repair work inside the apartments, as well as in any case where safety considerations make it necessary.
Mr Takhiaos referred to the uproar over the work, despite the building management’s approval. He said the objections came from a local group that was treating the issue as if it were involved in building the project.
“It is one thing to have agreed to keep people informed, and quite another to decide who makes the decisions,” he said. He also criticised those who, he said, had found an opportunity in Kypseli to “get in on the action”.
He referred to an Athens city councillor with no connection to the project or the area, who goes around with a megaphone outside the construction site to whip people up. “Both Elliniko Metro and the government are taking responsibility. The Metro must move forward seriously and in accordance with engineering and scientific principles,” he said.
The experience of Thessaloniki
Recalling his experience with the Thessaloniki Metro, Mr Takhiaos urged that the same mistakes not be repeated in Athens. As an example, he cited the uproar a few weeks ago when flooding at the Ministry of Foreign Affairs was blamed on the Metro, although the problems now appear more likely to be related to the Peisistratean Aqueduct.
“Let’s not start tomorrow blaming the Metro, and the Metro, and the Metro, for every problem that appears somewhere. We will turn a project that Athens badly needs into a joke,” he said. He recalled that Line 4 will serve Athens neighbourhoods with significant transport needs and will operate without a driver, following the same approach as the Thessaloniki Metro.
“It will transform Athens. We cannot turn it into a joke or an ordeal,” he added. He also called for a distinction to be made between the contracting consortium and Elliniko Metro, which is a state-owned company.
“Its people are highly experienced engineers who have built tunnels throughout Athens and know the ground beneath it very well. They are civil servants who have no reason either to put any resident’s safety at risk or to turn a blind eye to any oversight,” he said.
He noted that building movements and ground subsidence are being monitored continuously, both at the tunnel boring machine’s face and along the sections it has already passed through, and that monitoring will continue for many years. As for the timetable, Mr Takhiaos said it would be considered after the tunnel boring machine restarts.
“For now, our priority is to address the residents’ concerns and ensure they feel safe in their homes. The civil engineers who carried out the inspections say there is no immediate problem with any of the buildings,” the Deputy Minister for Infrastructure and Transport concluded.