The National Development Fund is moving plans for a government park at the former PYRKAL site on to the next stage, in an investment worth €422 million, as opposition to the project among local residents intensifies.
The four prospective investors are currently working on their proposals for the project contract, in a process expected to be completed in the coming period.
Binding bids are expected to be submitted in the first quarter of 2027. The GEK TERNA, AVAX-AKTOR Concessions and Metlen-Intrakat consortia have expressed interest in taking on the project.
However, the urban planning framework and changes linked to the annulment of provisions of the New Building Regulation (NOK) are causing major delays to the redevelopment, according to people familiar with the project.
Council of State ruling awaited
Meanwhile, appeals by two local bodies are pending before the Council of State. They are seeking to overturn the Environment and Energy Ministry’s (YPEN) decision approving the environmental provisions of the Special Urban Plan for the redevelopment.
The application for annulment was heard on 18 March 2026, and a ruling is awaited.
Event planned for 4 December
At the same time, local residents are preparing further protests, with the next rally scheduled for early December.
Specifically, on 4 December, a group of citizens and organisations that appealed to the Council of State is planning an event in Hymettus.
“The organisations and residents challenging the plan are raising questions about the overall economic cost, the density of development, the impact on traffic and the extent of green space that will actually be available,” they said in a statement.
“At the centre of the discussion is the alternative proposal to create a unified public space for green areas, sport, culture and health — a plan that had in any case been envisaged for the area for decades under the institutional framework that remained in force until recently,” they added.