A major tourism investment planned by EKTER at Kolymbithres on Paros has taken a new turn, with the municipality preparing to appeal to the Council of State, Greece’s supreme administrative court, seeking the annulment of the Presidential Decree approving the Special Urban Plan for the hotel complex.
In a unanimous decision on 18 November, the Paros municipal council authorised the Municipal Committee to take the necessary steps to commission legal and technical support for the case.
The development comes about a month and a half after the publication, on 12 October, of the Presidential Decree approving the Special Urban Plan for a 327.84-hectare site in the Naousa area.
The investment by listed company EKTER has a budget of €53.3 million and envisages a luxury hotel complex with capacity for 240 guests.
The municipality’s decision
According to the municipal council’s decision, the case was discussed as an urgent item outside the agenda to enable an application for annulment to be filed within the statutory 60-day deadline.
In his recommendation, Paros mayor Konstantinos Bizas reiterated the municipal authority’s opposition to so-called strategic investments, and specifically to the Kolymbithres Special Urban Plan, arguing that it provides for “the construction of a large hotel complex in a protected area of the island”.
As the decision notes, the municipality had already intervened in the Council of State’s review of the plan in the summer of 2025, submitting a brief through a specialist lawyer.
The municipal authority had also publicly expressed its disappointment after the country’s highest court issued a favourable opinion on the plan.
To prepare the appeal, the municipal council authorised the Municipal Committee to assign the legal work to the lawyer who had represented the municipality in the previous proceedings, while technical documentation is to be prepared by specialist urban planning consultancy Gimisis + Associates.
A key part of the technical documentation will be challenging the Special Urban Plan’s compatibility with the current local urban plan and the higher-level spatial plan for the South Aegean Region.
The investment and outstanding issues
EKTER’s project has a long history: the company acquired the site in stages in 2003 and 2004. The investment plan was subsequently revised, also in response to objections raised by the Council of State in 2023. The hotel’s planned capacity was cut from the original 440 to 240 beds, and the proposed built area was reduced.
The revised plan ultimately received a favourable opinion from the full bench of the Council of State, a development EKTER announced last July, paving the way for the Presidential Decree to be issued in October.
It should be noted that the decision authorises the necessary legal and technical steps; it does not itself approve the filing of the application for annulment.
What the project includes
EKTER’s investment, with a total budget of €53.3 million, involves the development of an ultra-luxury five-star resort on a 327.84-hectare site at Kolymbithres on Paros.
Under the plan reviewed by the Council of State, the hotel will have capacity for 240 guests, with 70 double rooms, 20 triple suites and 10 quadruple suites. The complex is planned to include restaurants, bars, swimming pools, spa facilities and wellness and rejuvenation amenities, as well as a luxury camping area (glamping).
Under the plan reviewed by the Council of State, about 80% of the total site is to remain undeveloped.
According to EKTER, funding for the project is secured and includes resources from the Recovery and Resilience Facility, bank borrowing and the company’s own funds.
Approval of the Special Urban Plan by Presidential Decree in October marked a significant step towards advancing the investment, but does not mean that all individual permitting procedures have been completed.