The investment plan for the former Agia Triada campsite in the Municipality of Thermaikos, Thessaloniki, provides for the creation of an organised holiday and tourism village with more than 200 homes and the development of a four-star hotel with 250 beds.
The planned development on a coastal site of more than 161 hectares is detailed in the Environmental Impact Assessment (EIA), prepared to support the issuance of the Joint Ministerial Decision (JMD) on the location of the Special Spatial Plan for the Development of Public Property (ESHADA). The study has been published for consultation as part of the process to secure an Environmental Terms Approval Decision (AEPO).
The investor is Cyprus-based Matenisa Trading Co. Limited, which is linked to the interests of the Melissanidis family. The company was named preferred bidder in the tender run by the Hellenic Republic Asset Development Fund (HRADF) for the site, offering €19.5 million.
The contract was signed on 31 July 2025, with the final price exceeding the starting price of €8.1 million in the electronic auction by 140.7%.
With the investment plans now set out in greater detail, the project is taking clearer shape. It aims to combine tourist accommodation with a holiday-home development along the Thermaikos coastline, with construction expected to take four years.
The EIA does not specify a total investment amount.
The holiday village
Under the ESHADA, approved by a Presidential Decree published in the Government Gazette on 24 July 2025, the site, covering 161,456.84 sq m, is divided into three distinct zones, each with different land uses and building terms.
The first zone, covering about 102 hectares, is intended for the development of the holiday and tourism village; the second, covering 37 hectares, is designated for tourism and leisure uses; and the third, covering 22.5 hectares, is a nature protection zone that includes forest land, where construction is not permitted.
In the first zone, the maximum permitted floor-area ratio is 0.2 and the maximum permitted site coverage is 20% of the zone’s total area. The maximum building height is set in accordance with the New Building Regulation (NOK). Buildings must be at least 10 metres from the boundaries of watercourses.
The residential part of the project предусматривает the development of 213 separate properties across three building blocks, covering a total area of about 50,845 sq m.
Based on the planning figures set out in the EIA, total floor space in the first zone, including the planned school building, will amount to 20,268.52 sq m, with total site coverage of 15,618.38 sq m. Both figures are within the permitted limits.
The homes will come in different types, mainly maisonettes and apartments, with two or three above-ground floors and basement areas. The architectural design prioritises views of the sea and communal spaces, and includes plans for internal courtyards, balconies, swimming pools and stepped layouts.
The site plan also provides for communal green spaces and an extensive network of pedestrian paths to ensure access to the seafront, as well as a school with capacity for about 300 pupils. The school building is expected to have a footprint of 1,208 sq m and two floors, with the final figures to be determined by the school’s facilities programme.
The hotel
For the hotel component, Matenisa Trading has opted for the condo hotel model, a type of hotel development that combines the services and amenities of a conventional hotel with apartments in the same building complex.
In the second zone, covering a total of 37,053.74 sq m, the maximum permitted floor-area ratio is also 0.2, while maximum site coverage is 50% of the zone’s total area. Hotel buildings may reach a maximum height of 18 metres.
Buildings must be at least 15 metres from the site boundaries. They must also be at least 50 metres from the coastline in the case of tourist accommodation and 30 metres in the case of homes up to 7.5 metres high.
The four-star hotel will be built in the southern part of the second zone, near the provincial road, and will have 250 beds as well as 25 apartments.
The building’s architecture will feature curved lines, with a design inspired by the shape of the sea and its waves. The aim is to integrate it more fully into the coastal landscape and make the most of views across the Thermaikos Gulf.
In addition to accommodation, the hotel will include reception, dining, leisure and wellness facilities, as well as underground parking. According to the planning figures set out in the study, the hotel buildings will have a total floor area of 7,403.61 sq m, a footprint of 3,124.10 sq m and a volume of 36,123.92 cubic metres.
Four additional detached maisonette-style homes with private outdoor spaces are planned in the northern part of the same zone, close to the sea.
The timeline
Under the indicative timetable included in the EIA, the construction phase is expected to last 48 months, with work scheduled to be carried out in stages and partly in parallel to reduce the time required to complete the project.
In addition to removing the old facilities and constructing the new buildings, the project includes the construction of all necessary internal infrastructure networks, from roads and water supply to drainage, irrigation and electromechanical systems.
The study’s authors say that the planned redevelopment of the former campsite, which is currently inactive, is expected to help upgrade the wider area’s tourism offering, strengthen the local economy and create jobs both during construction and once the facilities are operational.