Fresh hurdles have emerged in the licensing process for the strategic tourism investment being promoted on Ios by the Michalopoulos family, which owns the Calilo hotel group, after the Municipality of Ios identified a series of shortcomings in the study to delineate three watercourses in the area earmarked for development.
The investment plan of “105 S.A. Tourism and Technical Property Development Company” concerns a total area of about 566 stremmata (56.6 hectares) and is one of three strategic tourism investments, worth a total of €200 million, that the Michalopoulos family has set in motion on the Cyclades island, according to information from the Calilo group.
In a unanimous decision on 24 November, the Ios municipal council called for the file on the watercourses’ delineation to be completed and resubmitted, so that it can issue a final opinion on the proposal.
The development comes at a time when, more than six years after the project was first included in the strategic investments framework, approval of the Special Spatial Development Plan for Strategic Investments (ESCHASE) is still pending. As the municipal council’s decision notes, although public consultation on the Strategic Environmental Impact Assessment (SEIA) has been completed, the required Presidential Decree has not yet been issued.
The investment plan envisages the creation of an integrated tourism complex in the Koumbara-Diakopto area, as well as a five-star hotel and tourist residences in the Tzamaria-Faros areas.
The Municipality’s observations
The latest development centres on the final delineation study for three watercourses in the Koumbara-Diakopto area on the western side of Ios, which was sent to the Municipality of Ios by the Ministry of Environment and Energy last October.
According to the municipal technical service’s report, which was unanimously adopted by the municipal council, the submitted file does not meet the requirements of the current legal framework, showing “shortcomings both in the content of the individual deliverables and in how the study relates to existing and ongoing plans for the area”.
In particular, the decision notes that although the study was drawn up as part of the process to approve the ESCHASE, it does not take into account the plan’s provisions or the future drainage and water-flow conditions that will result from its implementation.
Among the main shortcomings identified by the municipal technical service are the absence of an Environmental Report containing the minimum information required by law; the failure to investigate historical flooding in the area concerned; a lack of supporting evidence for key assumptions in the hydraulic study; deficiencies in the topographic survey and accompanying technical report; and the absence of justification for the proposed alignment of the watercourse boundaries.
The technical service also says the study is not linked to either the Local Urban Plan for Sikinos, Folegandros and Ios, which is being drawn up, or the Strategic Environmental Impact Assessment for the ESCHASE.
The developable area
The technical service’s observations also include the possibility that the developable area of the investment plan, as well as the layout of the planned buildings, may need to be updated.
This point is linked to the fact that the ESCHASE’s Strategic Environmental Impact Assessment was based on an earlier study for the provisional delineation of the three watercourses, drawn up in March 2024.
Since the area within the watercourse boundaries has been excluded from the ESCHASE’s developable area, the technical service highlights the need to compare the boundaries in the latest study with those used in the plan. If they differ, both the developable area and the layout of the relevant buildings will need to be updated accordingly.
It should be noted that the municipal council’s opinion concerns only the file for the delineation of the watercourses, not the investment plan as a whole. However, it highlights the outstanding issues in the process to approve the ESCHASE.
The Michalopoulos family’s plans
The Michalopoulos family considers 105 S.A.’s investment the most advanced of the three strategic tourism developments being promoted on Ios. Its implementation is expected to create about 500 seasonal jobs. The family estimates that, if the final licensing steps are completed, work will begin in 2027.
According to information presented by the Calilo group, the investment plan is divided into two distinct zones: a development zone covering about 273 stremmata (27.3 hectares), or 48% of the property, and a protected zone extending over about 293 stremmata (29.3 hectares), equivalent to 52% of the total area. The plan also provides for about 2,826 sq m of land to be ceded to the Municipality.
The group’s plans also focus on developing the necessary infrastructure, including desalination plants, with the aim of limiting the strain on the island’s natural resources and existing networks.
The investment is part of the Calilo group’s broader strategy. The group owns land covering about 30% of Ios and has pledged not to build on more than 1% of its holdings.
The €200 million investments
As for the Calilo group’s projects on the Cyclades island, the Michalopoulos family plans to carry out its three major tourism projects on Ios in successive phases, with five to six years between each investment.
The first priority, according to the family’s plans, is 105 S.A.’s investment, while development in the Papa area will follow, where the luxury Calilo hotel is already located. The investment in the Pikri Nero area is planned for last.
The group says it has opted to phase the three investments, for which the ESCHASE planning tool has been chosen, because of the island’s ability to support projects on this scale, both during construction and once the tourism facilities are operational.
The Calilo group, which has operated in the hospitality and food service sectors on Ios since 2012, currently includes Calilo and Agalia Luxury Suites in its hotel portfolio.