Batteries: Next phase shaped by objections, with DEPA also set to appeal

The next phase following publication of the Ministry of Environment and Energy’s list of batteries to be given priority access to the grid is expected to be shaped by appeals. The number of objections will also determine the final timetable. DEPA is also set to appeal.

Batteries: Next phase shaped by objections, with DEPA also set to appeal

This article is an AI translation of an original piece published in Greek. Read original

The next phase following publication of the Ministry of Environment and Energy’s list of batteries with a combined capacity of 4.7 GW and estimated investment of nearly €2bn, which will be prioritised for connection to the grid, is expected to be shaped by appeals.

Objections from those left off the list, or placed on the reserve list rather than among the successful applicants, are considered certain. DEPA is among them and is expected to appeal against the evaluation committee’s decision, as none of its projects made it into the rankings.

Market sources say the high level of participation, combined with questions of interpretation around some of the project evaluation criteria, has significantly increased the likelihood of appeals by investors who ranked lower on the lists than they had expected.

Risk of delays

This in turn means the timetable for starting the process as a whole may slip, as connection terms can be issued to investors only after the relevant appeals have been examined, potentially delaying the entire programme.

Among the Ministry of Environment and Energy’s ranking tables for investments in batteries without state support, which will be the first to connect to the grid, are not only traditional Greek vertically integrated players and foreign companies with a presence in Greece, as Euro2day.gr reported, but also many small and medium-sized renewable energy producers and even retail chains.

The huge investment interest in storing and using the vast volumes of cheap midday energy that is currently “thrown away” is evident from the fact that, of the 831 applications (with a combined capacity of 12.3 GW) submitted in response to the Ministry of Environment and Energy’s call, 640 projects (with a capacity of 7.8 GW) made it into the rankings. Batteries with a capacity of up to 4.7 GW will receive connection terms.

Even if not all of the projects go ahead — banks are applying strict criteria because revenues from merchant batteries are not guaranteed and depend on wholesale market fluctuations — this would still represent one of the biggest waves of energy investment ever undertaken in Greece.

The government’s target is for 3-4 GW of batteries by 2028. But if applications for photovoltaic clusters (with an integrated battery) that connect to the grid at the same point are also included, the total rises to nearly 7 GW. That figure goes a long way towards meeting the country’s needs in the coming years.

Once the objections have been assessed, the next steps will be the issuance of final connection offers by IPTO and HEDNO. These will be issued in order of application priority and issuance will stop once the limits for each category have been reached: 3.8 GW on the Transmission System and 900 MW on the Distribution Network.

As soon as the connection terms are offered, the onus will shift to investors, who will have two months to decide whether to accept them.

If they withdraw, the hefty bank guarantee they have lodged will be returned. If they accept the connection terms, they must lodge a new guarantee of equal value; if they fail to complete the project within 18 months, it will be forfeited.