Le Figaro: France backs Greece-Cyprus undersea cable

The strategically important project for energy security faces obstacles amid disputes with Turkey.

Le Figaro: France backs Greece-Cyprus undersea cable

This article is an AI translation of an original piece published in Greek. Read original

Tensions have been running high for several days between Athens, Nicosia and Ankara. Diplomats are on alert, while energy markets are watching developments with concern. At the centre of this crisis in the eastern Mediterranean is a 1,208-kilometre undersea electricity cable intended to connect Crete with Cyprus and Israel, Le Figaro writes in an article on the GSI.

The project, with a total cost of €1.9 billion, is backed by Brussels and being advanced with the involvement of French interests, including Nexans, which will supply the cables, and investment fund Meridiam, its main shareholder and principal financier. However, it has been frozen since 2024 because of maritime disputes between Greece and Turkey.

Paris is seeking to play a mediating role to prevent this strategically important European project from becoming a new diplomatic flashpoint. Since the evening of Tuesday, 10 November, a series of NAVTEX notices has been exchanged in the area, through maritime warnings issued before vessels set sail.

“The coming days will be critical,” warns Konstantinos Filis, director of the Institute of International Relations in Athens.

When the French vessel Abeille Marengo sailed from the port of Heraklion in Crete on Tuesday evening to carry out the seabed surveys needed for the cable-laying work, its crew knew the mission would be difficult.

A few hours after it set sail, Ankara issued a NAVTEX claiming that the work had been coordinated with the Turkish authorities and that they had given their consent. Athens and Nicosia immediately disputed this interpretation.

Greece issued a counter-NAVTEX, declaring the Turkish NAVTEX invalid and without legal effect. Cyprus issued a similar notice, reiterating that the work within its Exclusive Economic Zone had been approved by the competent Cypriot authorities.

Behind this dispute over NAVTEX notices lies a broader issue. At a time of intensifying regional competition over maritime boundaries and eastern Mediterranean hydrocarbons, the question is who has the right to approve projects in disputed waters.

“For Ankara, issuing a NAVTEX is a way of signalling that no project can proceed in the area without its approval. For Athens and Nicosia, it is unthinkable to recognise any Turkish right to control work approved by their own authorities,” explains a European diplomat serving in Greece.

The Greek government says that no request for a permit was ever submitted to Ankara.

These tensions are not insignificant. The energy stakes are particularly high.

“The Great Sea Interconnector (GSI) is not simply a technical infrastructure project. It will connect the electricity systems of Greece and Cyprus via a high-voltage direct current (HVDC) undersea cable capable of transmitting electricity in both directions.

This means Israel will be able to receive European electricity in the event of an energy crisis or an attack. At the same time, it gives Europe a significant strategic advantage in relation to Israel,” says Konstantinos Filis.

The project is equally crucial for Cyprus, which remains the last European Union member state not connected to the European electricity grid.

“Today, the island operates an isolated electricity system, and its power generation remains heavily dependent on imported fossil fuels,” the professor adds.

The cable will give Cyprus access to electricity generated in the European mainland market, while also allowing it to export surplus power when renewable generation, mainly from solar panels, increases.

The undersea route between Crete and Cyprus is about 900 kilometres long, with an initial transmission capacity of 1,000 MW. In some places, the cable will have to be laid at depths of nearly 3,000 metres, making the project exceptionally demanding from a technological and industrial perspective.

The financial side is also significant. Of the total estimated cost of €1.94 billion, the European Union has already approved a grant of about €657 million through the Connecting Europe Facility.

The project is being developed by a company that is 66% owned by France’s Meridiam and 34% by Greece’s IPTO. With Nexans as the cable manufacturer and supplier, France’s involvement is far from symbolic. It is financial, industrial and now diplomatic.

Meridiam’s entry into the project’s shareholding on 5 August gave fresh impetus to infrastructure that had been delayed for a long time. Nexans, for its part, is directly affected by the permits required for both the seabed surveys and the progress of the work.

For Paris, the stakes also include protecting French commercial interests in a region where energy infrastructure has become an instrument of geopolitical power.

For now, the timetable remains precarious. Survey work had already been abruptly halted in 2024, when Turkey deployed warships south of Kasos and Karpathos.

Resuming the surveys is therefore a key step. Before the cable can be laid, the seabed must be accurately mapped and the technically safest route identified.

The new target for completing the project is now 2031, while the final cost could exceed the initial estimates.

Nevertheless, according to Konstantinos Filis, “France’s involvement this time is a guarantee that the project will be completed successfully.”

Paris faces the challenge of preventing tensions from escalating, so that neither Cyprus’s energy security nor the credibility of European interconnection projects and the European Union’s ambitions to diversify its energy sources are put at risk.