The long-awaited publication of the list of hundreds of projects set to receive priority grid connections is mobilising investment in batteries by small and large groups, with total investment potentially reaching €2bn.
From established Greek vertically integrated players to foreign companies active in Greece, and from small and mid-sized renewable energy producers to major retail chains, the Ministry of Environment and Energy’s ranking tables for battery investments without state support that will be first to connect to the system feature a broad mix of players.
The scale of interest in investing in energy storage and making use of the vast quantities of cheap midday power that are currently “thrown away” is clear from the figures. Of the 831 applications submitted to the Ministry’s call, with a combined capacity of 12.3 GW, 640 projects with a capacity of 7.8 GW made it onto the ranking tables. Batteries of up to 4.7 GW in total will receive connection terms.
Even if not all these projects go ahead — banks are applying strict criteria, as revenues from merchant batteries are not guaranteed and depend on wholesale price fluctuations — this would still amount to the launch of one of the largest waves of energy investment ever undertaken in Greece.
The government’s target is 3-4 GW of batteries by 2028. But if applications for photovoltaic clusters with integrated batteries connecting to the system at the same point are also included, the total approaches 7 GW.
This figure covers a large share of the country’s needs for the coming years.
Winners in the battery race
A closer look at the ranking tables for applications seeking connection terms through fast-track procedures shows that the strongest presence is from PPC, Protergia, Motor Oil, TERNA Energy, Helleniq Renewables, AKTOR and Principia.
Other strong contenders include French company EDF, Interphoton, Rokas, Lightsource, Germany’s ABO Energy and Aenaos.
PPC appears to be leading the field, with projects totalling 470 MW: five in the lignite phase-out zones (425 MW) and a sixth at Meliti, in Florina (45 MW). But the 500 MW anti-concentration limit — the cap on the maximum battery capacity a group can own or represent — means it cannot complete all of these projects, particularly as it is also developing 150 MW of batteries from previous tenders.
According to reports, it will therefore choose to build 250 MW of batteries from its total portfolio under the call.
Other significant portfolios include Protergia’s six qualifying batteries, with a combined capacity just under 200 MW; Motor Oil’s 220 MW; TERNA Energy’s 200 MW; and Helleniq Renewables’ 170 MW.
GEK TERNA Group appears to have two batteries totalling 150 MW, plus another 50 MW project from its subsidiary Optimus Energy, which is on the reserve list. AKTOR (100 MW in Western Macedonia) and Principia (45 MW) each have one project on the ranking tables.
A breakdown of the projects set to connect to the transmission system (IPTO) reveals surprisingly little market interest in battery investments backed by signed bilateral contracts with industrial companies. Of the 500 MW reserved in the system for such projects, applications were submitted for just 238.5 MW.
This first category includes just six projects, among them a 50 MW battery from Motor Oil, through its subsidiary MS Korinthos I, and a 25 MW battery from Helleniq Renewables at the industrial facilities of its parent company’s refinery in Thessaloniki.
Retail and energy-intensive chains
In the second category, for batteries operating under similar contracts with other businesses, the only applicant is Metro Energy (20 MW), owned by the Panteliadis family, which controls, among other businesses, the My market and METRO Cash & Carry chains.
In the third category, for batteries to be included in the portfolios of Aggregation Representatives (FoSEs), the 300 MW cap has been exceeded by players including GEK TERNA subsidiaries Blue BESS (50 MW) and NXA Energy (100 MW), as well as Enerwave of Helleniq Energy.
In the fourth category, covering lignite phase-out zones, PPC is dominant. The fifth and final category is a general one covering all other standalone batteries; 108 different projects have been ranked, from large companies to smaller ones such as Interphoton.
Hundreds of small projects
Small and mid-sized players have made an impressive showing among the batteries set to connect to the distribution network (HEDNO). In the smallest category, for projects with capacity below 1 MW, the ranking tables include 339 projects with a combined capacity of about 334 MW, against available capacity of 211.7 MW.
Similarly, 97 battery projects with capacity of 1-5 MW, totalling about 424 MW, are competing for just 211.7 MW of available grid capacity. The projects amount to twice the capacity on offer.
What comes next
After the ranking tables have been drawn up and the objections — which are certain to follow — have been assessed, IPTO and HEDNO will proceed to issue Final Connection Offers.
Offers will be issued according to the priority order of applications, and the process will stop once the limits for each category have been reached: 3.8 GW for the Transmission System and 900 MW for the Distribution Network.
Once connection terms have been offered, the ball will be in the investors’ court: they will have two months to decide whether to accept them.
If they withdraw, their “hefty” bank guarantee will be returned. If they accept the connection terms, they must submit a new guarantee of equal value; if they fail to complete the project within 18 months, it will be forfeited.
The financing challenge
In reality, the game begins when investors receive their connection offer, as they must secure financing for the project within the two-month deadline.
While the major players have credit lines in place and are not concerned about financing, all the others will have to meet the increasingly strict “filters” applied by banks. The banks are being asked to lend on a large scale for a new technology whose future revenues are entirely uncertain.
Those revenues track wholesale market fluctuations, so financing depends not only on the investor’s creditworthiness and track record, but also on a wide range of factors.
These include any guaranteed revenues the investor can secure, the type of equipment and its maintenance over the battery’s entire life cycle, the Aggregation Representative involved and the stability services provided to the system.